Which of the following is NOT typically a part of disaster recovery planning?

  1. risk assessment

  2. inventory management

  3. impact analysis

  4. load balancing

The correct answer is: load balancing

Disaster recovery planning focuses on the strategies and processes that organizations implement to recover from unexpected disruptions, such as natural disasters, cyberattacks, or system failures. Key components of this planning include risk assessment, which involves identifying potential threats, and impact analysis, which assesses the consequences of those threats on business operations. Inventory management can also be relevant in disaster recovery planning, particularly in understanding what resources and assets either need to be protected or can be restored quickly. Load balancing, on the other hand, is primarily a technique used to distribute network or application traffic across multiple servers or resources to ensure optimal performance and resource utilization. While load balancing plays a crucial role in maintaining service availability and performance during regular operations, it is not a direct part of the disaster recovery planning framework. Instead, it aims to enhance system resilience and efficiency rather than focusing on recovery processes. Thus, it is the component that does not typically align with the core aspects of disaster recovery planning.